CMiC Field - QC Inspection and Testing Plan
QC Inspection and Testing Plan; Standard Treeview path: CMiC Field > Site Management > QC Inspection and Testing Plan
Quality control inspection and testing plan records can be created as submittals in this screen. These records can be used to record, for example, the results of strength tests of concrete samples of every pour of concrete that is carried out for a project. In this case, each item record would represent the individual test and result.
NOTE: The Quality Control (QC) feature and its associated screens have been deprecated (e.g., CMiC Field - QC Inspection and Testing Plan, CMiC Field - System QC Classifiers, CMiC Field - QC Inspection and Testing Plan in Daily Journals, CMiC Field - QC Phase Values, and CMiC Field - Definable Feature Of Work Values).
For more information on submittals, please refer to the Submittals screen.