Scheduling 2.0 - Calculations for Free Float and Total Float
NOTE: Scheduling 2.0 has been deprecated and is no longer supported by CMiC. See Product End of Support for further details.
Early Start (ES) = earliest start date of activity without affecting the project's start date.
or
Early Start = Early finish of predecessor.
Early Finish (EF) = Early Start + activity duration (including the resources assigned that also affect duration).
Late Start (LS) = Late Finish - activity duration (including the resources assigned that also affect duration).
Late Finish (LF) = latest end date of activity without affecting the project's end date.
or
Late Finish = Late start of successor
Early Float (EFS) = Difference between early start and late start.
Late Float (LFF) = Difference between early finish and late finish.
Free Float = Difference between activity end date and activity's earliest successor start date.
Total Float = Minimum between early float and late float.