Activities
NOTE: Scheduling 2.0 has been deprecated and is no longer supported by CMiC. See Product End of Support for further details.
In the Activities section, there are a number of columns which are displayed by default:
-
Activity Name
-
Start Date
-
Finish Date
-
Resources
The vertical bar which separates the Activities section from the schedule can be dragged to the right to show all the columns.
Columns can be added to the Activities section by clicking on the down arrow in the header of Add Column, as shown in the picture below, and then clicking on the field you want added.
Columns can be removed by clicking on the down arrow in the header of any existing column, as shown in the screenshot below, and deselecting the columns you wish to remove.
Activity Name
An activity is a task to be carried out as represented on the schedule. The activity must have a start date and an end date.
Duration
The duration is automatically determined from the Start Date and Finish Date fields.
Resources
This column has an LOV of project contacts, from which personnel assignment can be made against the activity.
%Complete
This is the percent completion of the activity, and is represented on the schedule by a purple-colored bar. For a higher-level summary activity, the percent completion is based on the progress of the sub-activities, and is shown as a pale-yellow bar at the summary activity level.
Baseline Finish, Baseline Start
These fields display the baseline schedule’s finish and start date.
Bid Item
This will open the Bid Item LOV so bid items can be assigned to the activity.
Early Start Date
Earliest start date of the activity without affecting the project's start date.
Early End Date
This is the early start date plus the activity duration (including the resources assigned that also affect duration).
Free Float
The difference between the activity end date and the activity's earliest successor start date.
Late End Date
The latest end date of the activity without affecting the project's end date.
Late Start Date
The late end date minus the activity duration (including the resources assigned that also affect duration).
Notes
Enter notes for the activity.
Scheduling Mode
Select the appropriate scheduling mode.
Total Float
The minimum between the early float and late float.