Enter PCI - Change Management
Pgm: PMCHGFM – Potential Change Items; standard Treeview path: Change Management > Change Orders > Enter PCI – General tab
The creation of a Potential Change Item (PCI/Change Order) has the potential to change the following:
-
Cost budget (JC budget) associated with job.
-
Client’s bill (JB contract) associated with job.
-
Vendor Subcontracts on the job – specified using Vendor and Contract fields on Detail tab.
-
Contract Forecasting forecasts.
For an overview of PCI basics, please refer to PCI Basics – Quick Guide.
NOTE: When a job does not allow transactions, PCIs can still be entered to adjust budgets, when the ‘Allow PCI Entry’ checkbox is checked at the job level (standard Treeview path: Job Costing > Job > Enter Job – Settings tab).